Title
ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE TAYLOR RANCH ELEMENTARY SCHOOL - HVAC RENOVATION: BUILDING #5 PROJECT

Description

The engineer has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.



Recommendation
That the work performed by P.J. Hayes Inc., dba Tandem Construction, for the Taylor Ranch Elementary School - HVAC Renovation: Building #5 project be accepted as substantially complete as of 8/22/2007.

Contact
LEMPE & COLLINS

Financial Impact
N/A


Attachment:  BAIenc12-11-07TayRnchHVAC-Bldg5-SC.pdf